The Details
Project Name: Kings Plaza Parking Garage
Project Start: October 2013
Project Completion: November 2014
The Kings Plaza Parking Garage Project was a complete structural and aesthetical renovation of a 1,000,000 ft2, 10-story parking garage. The construction was phased throughout the duration of the project to allow the garage to remain active. A brief overview of the scope of work included:
- Shoring, barricades, and traffic control
- Asphalt repair/replace
- Topping slab repair/replace
- Precast Tee Repair (stems, flanges, columns, beams, girders, etc.)
- Cast-in-place and curb concrete repair/replace
- Expansion joints
- Steel repair and coating
- Steel railing
- Painting
- Drainage